Cofra passes the 10 million meter mark on the N23 Westfrisiaweg!

  • Last month Cofra installed the 10 millionth meter of vertical drain (type MD7407) on the project N23 Westfrisiaweg. This project is an exceptionally large work for Cofra in The Netherlands. A road section of about 40 kilometers is reconstructed and the vertical drains must be installed in different phases along this section. The first meters have been installed in 2014 and the project is expected to be completed early 2017. Due to the tight schedule and the deployment of multiple base units maximum productions were achieved of up to and over 80,000 meters per day and all deadlines were met. This would not have been possible without the good relationship with our customer Heijmans.